Limonite Avenue Construction Notice: October 14 - 19, 2019

Post Date:10/14/2019 7:34 AM

Limonite Progress Schedule 

Construction is focused on Stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

The contractor will be performing various tasks in preparation for opening the new Limonite Avenue Bridge on the night of October 19, 2019. See the schedule below for the closures for this week.

 Schedule  Closures
Monday and Tuesday, October 14 - 15, 2019

9:00pm - 5:00am

Wednesday to Saturday, October 16 - 19, 2019
9:00pm - 5:00am

Two outside lanes of I-15 both directions

SB I-15 on and off ramps closed.

Two outside lanes of I-15 both directions
All I-15 Ramps at Limonite Avenue closed
Limonite Avenue full closure.

 

For full construction notice click here. 

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer