I-15 Limonite Avenue Interchange Project

Post Date:07/22/2019 9:23 AM

Construction is focused on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

The contractor will be pouring the support structure of the north side of the Limonite Bridge on Monday, July 22. See schedule below for affected traffic lanes.

The contractor will be closing the existing northbound on-ramp and opening the new northbound loop on-ramp. Traffic will be diverted from the existing northbound on-ramp to the new northbound loop on-ramp.

 Schedule  Closure
 Monday, July 22, 2019 - 8:00 p.m. - 5:00 a.m.  Outside WB lane closure on Limonite Ave Bridge
 Monday, July 22, 2019 - 9:00 p.m. - 5:00 a.m.  Outside NB I-15 lane closure
 Monday, July 22, 2019 - 9:00 p.m. - 4:00 a.m.  Outside SB I-15 lane closure
 Monday, July 22, 2019 - 11:00 p.m. - 4:00 a.m.  Middle SB I-15 lane closure
 Wednesday, July 24 at 5 a.m.  Traffic will be switched from the existing NB on-ramp to the new NB loop on-ramp
 

July+24+traffic+switch+map

Download full construction notice here.

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer