I-15 Limonite Avenue Interchange Project

Post Date:05/06/2019 11:35 AM

I-15 Limonite Avenue Interchange Project

Construction Update: May 5, 2019 - May 11, 2019 

Limonite Progress Schedule 

Construction is in stage 2B. Field activities will consist of the construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

The contractor will complete the demolition of the old bridge support structures for the north side Limonite Avenue Bridge. Foundations for the support structures of the new bridge are being constructed. The 2 outside lanes of the NB I-15 will be closed Monday night from 9 p.m. to 4 a.m.

Schedule

Closure

May 6, 2019 9 p.m. - 4 a.m. NB I-15 closure of 2 outside lanes

Limonite Picture

Download full notice here.

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer