I-15 Limonite Avenue Interchange Project

Post Date:04/29/2019 10:34 AM

I-15 Limonite Avenue Interchange Project

Construction Update - Week of April 21 - 27, 2019

Limonite Progress Schedule 

Construction is focused on stage 2B. Field activities will consist of the construction of the south side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

The demolition of the north side of the Limonite Avenue Bridge will take place on Friday night, April 26, 2019 and Saturday night, April 27, 2019. Limonite Avenue will be closed at 8 p.m. each night. The I-15 will be closed at 9 p.m. on Friday and 8:30 p.m. on Saturday. All closures will end at 8 a.m. See map for detours.

Schedule Closures
Friday, April 26, 2019

Closure of Limonite Avenue 8 p.m. to 8 a.m.

Closure of I-15 9 p.m. to 8 a.m.

Saturday, April 27, 2019

Closure of Limonite Avenue 8 p.m. to 8 a.m.

Closure of I-15 8:30 p.m. to 8 a.m.

 

April+26+27+closures+map


Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer