I-15 Limonite Avenue Interchange Project - Closure April 7 - 13, 2019

Post Date:04/10/2019 10:21 AM

I-15 Limonite Avenue Interchange Project

Construction Update - Ten Day Ramp Closure April 7 - 13, 2019

Limonite Progress Schedule 

The contractor is nearing completion of construction stage 1C and 1D and is beginning work on Stage 2A. Field activities will consist of construction for portions of the NB on-ramp and SB off-ramp.

Ramp and Street Closures

The 10 day ramp closure is still in effect this week. In addition to that, the NB I-15 will be closed on Friday night, April 12, 2019 and Saturday night, April 13, 2019  from 9 p.m. to 5 a.m. along with Limonite Avenue and SB ramps. The detour for the NB I-15 closure will be to exit at NB I-15 off-ramp and re-enter freeway at NB I-15 on-ramp. Limonite Avenue will be closed Thursday night. Ramp closure detour will use the on- and off-ramps at Cantu-Galleano Ranch Road, and Limonite Avenue closure will use the standard detour along Wineville Avenue, Cantu-Galleano Ranch Road, and Hamner Avenue.

*Please note: the exit to the Eastvale Gateway Center between City Hall and the Edwards Cinema will be closed through the remainder of the project however, the entrance will be open.

Schedule

Closures

Thursday night

April 11 from 9 p.m. to 5 a.m.

Full closure of Limonite Avenue

Friday and Saturday nights

April 12 and 13 from 9 p.m. to 5 a.m.

Full closure of NB I-15

Full closure of Limonite Avenue

Full closure of SB ramps

 

 

April+11+12+closures+map

Download full construction notice here. 

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer