I-15 Limonite Avenue Interchange Project: April 2, 2019

Post Date:04/01/2019 8:25 AM

I-15 Limonite Avenue Interchange Project: Full Closure April 2, 2019 

Limonite Progress Schedule 

Construction is nearing completion of stages 1C and 1D, and is now beginning to work on Stage 2A. Field activities will consist of construction for portions of the NB on-ramp and SB off-ramp.

Ramp and Street Closures

The NB and SB I-15 will have the outer 2 lanes closed on the night of April 2. Limonite Avenue will also be closed while traffic is switched from the north side of Limonite Avenue to the south side of Limonite Avenue. All ramps will also be closed. The closure will begin on the night of April 2 at 8pm and will open at 5am.

Closures for the rest of the week can be seen in the 10 Day Ramp Closure Notice.

Schedule Closure
Tuesday, April 2 at 8 p.m. to 5 a.m.

Full closure of I-15 freeway

Full closure of Limonite Avenue

 

detour map for april 2, 2019

Click the full construction notice for more information.

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer