I-15 Limonite Avenue Interchange Project Construction Update

Post Date:01/06/2019 8:26 AM

 I-15 Limonite Avenue Interchange Project Construction Update 

Week of January 6, 2019 - January 12, 2019

Construction this week will focus on stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing ramps and outside lanes of the I-15 Freeway on Monday and Tuesday, January 7 - 8, 2019.

Schedule   Closure

Monday night, January 7

9 p.m. to 6 a.m

 NB and SB I-15 closure outside lanes

Full closure of all ramps

 Tuesday night, January 8

9 p.m. to 6 a.m

NB I-15 closure of outside lane

Full closure of NB ramps 

 

Detour+Map+Jan+7

Detour+Map+Jan+8

For full notice click here

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer