I-15 Limonite Avenue Interchange Construction Update

Post Date:12/03/2018 9:30 AM

I-15 Limonite Avenue Interchange Project

Construction Update December 2, 2018 - December 3, 2018

Limonite Progress Schedule 

Construction will focus on stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing alternating lanes on NB and SB I-15 on Monday, December 3, 2018 through Friday, December 7, 2018 from 9 p.m. to 5 a.m. A minimum of one lane will remain open in each direction at all times.

 

Limonite Limonite Project Update

 

For more information please visit : http://bit.ly/2Ua73Yd

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer