Annual Overlay Street Maintenance Project Update

Post Date:11/30/2018 3:31 PM

Annual Overlay Street Maintenance Project Update

Due to heavy rain this weekend, the completion of work has been delayed. The work will continue as soon as weather and road condition permits. Here is another update to the Annual Overlay Street Maintenance Project: 

Traffic Signals:
All intersections have been equipped with video detection cameras, and five (5) intersections along Archibald Ave (at Schleisman Rd, Soleil Dr, Smith River Rd, Chandler St and Fieldmaster St) are fully operational. Following intersections are estimated to be fully operational by early December 2018:

  • Archibald Ave and Grapewin St
  • Archibald Ave and Whispering Hills Dr
  • Schleisman Rd and Enclave Dr
  • Schleisman Rd and Gypsum Creek Dr
  • Limonite Ave and Harrison Ave
  • Limonite Ave and Cloverdale Marketplace
  • Hamner Ave and Amberhill Ave 

Striping:

All lane lines along Archibald Ave, Limonite Ave, Schleisman Rd and Hamner Ave are installed. Remaining miscellaneous striping and signing including legends, crosswalks, raised pavement markers and hatched lines for bicycle lanes will be completed by early December 2018.

Please be advised that these timelines are subject to change depending on weather conditions and contractor’s availability. If there are changes to the schedule, another update will be provided to the public.

We appreciate your patience and cooperation as this project approaches completion. For more information, please contact our Public Works Department at 951.703.4471.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer